Does the GMP's rod need to be near to the power transformer body or in the tubulation is acceptable?

Created by Deleted Agent, Modified on Wed, 10 Aug, 2022 at 4:11 PM by Patrícia Siqueira

We don’t recommend installing the GMP in the tubulation due the oil flux is not quick enough, which prejudices the sensor measurement. The suggestion is to install it on the point with the highest oil circulation.

Pay attention to the valve size where the installation will do. If the rod is much bigger than the valve, there is the possibility of prejudicing the transformer isolation.

To know more about the GMP installation places, take a look at the guide: